Pagar sementara dari seng gelombang, tinggi 2 meter(m1) (SNI 03-2835-03)(AHSP-PU: A. 2.2.1.2)

URAIANSATKoef. HARSAT  UPAH  BAHAN  ALAT  JUMLAH 
2201Pekerja.oh 0.40  80,814.96  32,325.98  -    -    32,325.98 
2206Mandor.oh 0.02  123,988.39  2,479.77  -    -    2,479.77 
2214Kepala Tukang Kayu.oh 0.02  109,596.89  2,191.94  -    -    2,191.94 
2252Tukang Kayu.oh 0.20  95,192.55  19,038.51  -    -    19,038.51 
21102Semen PCkg 2.50  1,284.00  -    3,210.00  -    3,210.00 
21205Agregat Pecah Mesin 20-30 mmm3 0.01  269,954.58  -    2,429.59  -    2,429.59 
21249Pasir betonm3 0.01  164,368.05  -    821.84  -    821.84 
22201Pakukg 0.06  20,386.71  -    1,223.20  -    1,223.20 
26011Dolken Kayu Dia 8 cmbtg 1.25  24,610.00  -    30,762.50  -    30,762.50 
26093Usuk 4: 5/7 (Meranti)m3 0.07  3,745,000.00  -    269,640.00  -    269,640.00 
27119Cat meni besikg 0.45  50,097.40  -    22,543.83  -    22,543.83 
28015Atap Seng Gelombanglbr 1.20  77,361.00  -    92,833.20  -    92,833.20 
Jumlah 56,036.20  423,464.16  -    479,500.36 