Sunday, October 30, 2016

Pagar sementara dari kayu, tinggi 2 meter(m1) (RSNI T-12-2002-01)

URAIANSATKoef. HARSAT  UPAH  BAHAN  ALAT  JUMLAH 
1201Pekerja.oh 0.40  80,814.96  32,325.98  -    -    32,325.98 
1206Mandor.oh 0.02  123,988.39  2,479.77  -    -    2,479.77 
1214Kepala Tukang Kayu.oh 0.02  109,596.89  2,191.94  -    -    2,191.94 
1252Tukang Kayu.oh 0.20  95,192.55  19,038.51  -    -    19,038.51 
11102Semen PCkg 5.50  1,284.00  -    7,062.00  -    7,062.00 
11205Agregat Pecah Mesin 20-30 mmm3 0.01  269,954.58  -    2,429.59  -    2,429.59 
11249Pasir betonm3 0.01  164,368.05  -    821.84  -    821.84 
12201Pakukg 0.06  20,386.71  -    1,223.20  -    1,223.20 
16011Dolken Kayu Dia 8 cmbtg 1.25  24,610.00  -    30,762.50  -    30,762.50 
16093Usuk 4: 5/7 (Meranti)m3 0.07  3,745,000.00  -    269,640.00  -    269,640.00 
17038Residu/Terltr 0.40  6,955.00  -    2,782.00  -    2,782.00 
Jumlah 56,036.20  314,721.13  -    370,757.33 